/ TIMBER FRAME & SURFACE CLADDING
Date: Date: May 2017
Duration: 20 Weeks
The project shown comprised the construction of a large private dwelling with traditional foundations and a Timber Frame superstructure with enhanced U values being provided by high-performance insulation within the timber frame.
The superstructure was erected to watertight within 1 week allowing the internal finishing trades to commence while the external skin was being completed.
The project was substantially completed in a 20 week period including substructures.
Below are a list of the works which were implemented on this particular project.
– Joinery
– Shuttering