Timber Housing

01 May 2017 / By admin
/ TIMBER FRAME & SURFACE CLADDING

Date: Date: May 2017
Duration: 20 Weeks

The project shown comprised the construction of a large private dwelling with traditional foundations and a Timber Frame superstructure with enhanced U values being provided by high-performance insulation within the timber frame.

The superstructure was erected to watertight within 1 week allowing the internal finishing trades to commence while the external skin was being completed.

The project was substantially completed in a 20 week period including substructures.

Below are a list of the works which were implemented on this particular project.

JOINERY

– Joinery
– Shuttering