McDonalds DriveThru, Gateshead
SinCera were engaged by Key Property Solutions (KPS) to carry out major groundworks (side by side Drive-Thru renovation) to the external perimeter of the site, as well as the complete construction of a new external storage area and internal fit out works (tiling and general civil works).
McDONALDS, GATESHEAD
GROUNDWORKS / CONSTRUCTION RE-FIT
Client: KPS
Date: July 2016
Duration: 6 Weeks
Value: Circa £150k
In the early phases of the project the scope was changed considerably and SinCera aided the main contractor in resourcing and working to a new program, ensuring the project was handed over on time and to the clients satisfaction.
Below are a list of the works which were delivered on this particular project:
- Double drive-thru conversion
- Paving
- Drainage
- Resurfacing
- New build external storage
- Structural openings
- BWIC
- Tiling
- Joinery